Checklist
Washington DC permit submittal checklist (accelerated plan review)
DC Department of Buildings accelerated plan review accepts only a 100% complete drawing set on the day of upload. This checklist covers floor plans, elevations, sections, seals, and the District submission checklist required with the package.
Sources checked 2026-11-17
Want a quick estimate first? Try the Permit pack, or start free for Permits: track every item, who owes it, when to start, and a completeness check before anyone signs. Build free — pay only when you sign off.
| # | Item | Who provides it | Needed? | If it's missing |
|---|---|---|---|---|
| 1 | Complete construction drawing set
| Your team | Required | The package is not a submittal, and the review clock never starts. |
| 2 | The jurisdiction's own completeness checklist, filled in and uploaded | Your team | Required | A complete set can still be refused as an incomplete submittal because the checklist was not attached. |
| 3 | Structural, mechanical, electrical and plumbing drawings | Your team | If applicable | Trade permits cannot be issued, and later submittals may be billed or returned. |
| 4 | Professional seals or stamps in the form the jurisdiction accepts | Your team | Required | Unsealed drawings are treated as inadequate and are not reviewed. |
| 5 | Planning, zoning or land-use approval, where the project needs it | Third party | If applicable | The building permit cannot be issued ahead of the land-use decision. |
| 6 | Site plan, grading and stormwater documents | Your team | If applicable | The submittal is returned for a missing discipline rather than reviewed with comments. |
| 7 | Energy code compliance documentation | Your team | If applicable | Code review stops at the energy chapter. |
| 8 | Owner or contractor authorisation and the application form | Client | Required | The applicant is not established and the application is not accepted. |
| 9 | Fees paid at the rate the jurisdiction applies | Client | Required | The clock does not start until payment clears. |
| 10 | Deferred submittal list, where any portion is deferred | Your team | If applicable | A deferred scope that the jurisdiction does not accept sinks the whole application. |
Download this checklist as a PDF — 10 items, who owns each one, its start-by date, and what happens if it is missing. No email needed.
When to start each item
An example schedule, counted back from the due date. Confirm the rules for your matter before you treat any date as safe.
- Complete construction drawing set — start 60 days before the due date
- The jurisdiction's own completeness checklist, filled in and uploaded — start 20 days before the due date
- Structural, mechanical, electrical and plumbing drawings — start 45 days before the due date
- Professional seals or stamps in the form the jurisdiction accepts — start 30 days before the due date
- Planning, zoning or land-use approval, where the project needs it — start 120 days before the due date
- Site plan, grading and stormwater documents — start 45 days before the due date
- Energy code compliance documentation — start 30 days before the due date
- Owner or contractor authorisation and the application form — start 30 days before the due date
- Fees paid at the rate the jurisdiction applies — start 10 days before the due date
- Deferred submittal list, where any portion is deferred — start 20 days before the due date
Complete means complete on the day of upload
A hundred-percent set means every sheet the project needs, not every sheet currently drawn. A package submitted with a note that sections are to follow is not a partial expedited submittal; it is an incomplete one, and the accelerated route does not apply to it.
The jurisdiction's checklist is part of the package
The District requires a fully completed submission checklist in the application package. It is one page, it costs nothing, and it is the row that most often separates a package that gets reviewed from one that gets sent back.
Compliance does not get relaxed for speed
Accelerated review changes when the review happens, not what the review checks. Code compliance remains the standard, so compressing the schedule by submitting early with unresolved code questions moves the problem rather than solving it.
Same checklist rows, with an owner and a start-by date on each one. Or open the client-side sample first — nothing to install.
Related: Madera CA permit submittal checklist (residential completeness), All package checklists, The client-side sample
Keep reading
FAQ
- Does accelerated review guarantee a permit?
- No—accelerated review does not guarantee a permit. It changes the review queue, not the outcome. The District's own guidance is explicit that code compliance remains essential, so a fast review of a non-compliant set is still a non-compliant set.
- Can the submission checklist be completed after upload?
- No — the DC Department of Buildings accelerated programme expects the completed submission checklist in the package at upload. Without it, the submittal is treated as incomplete and you rejoin the queue.
- What if part of the design is not finished?
- No—the missing discipline has to be complete before upload, or the project is not an accelerated candidate. Submitting a set with an unresolved portion risks the whole application, not just that sheet.